United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project G617, Blue Earth County
Onshore wind project G617, Blue Earth County is a 50.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Blue Earth County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2006 (completed)
- Withdrawn / abandonedJul 2012 (project stopped here)
- ConsentedJul 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G617
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE Amboy - Willow 69 kV
- Location
- Blue Earth County, Minnesota
- Technology
- Wind: 50.0 MW
- Total requested
- 50.0 MW
- Study phase
- DPP - SIS
- Queue status
- Withdrawn
- Entered queue
- 11 April 2006
- Agreement signed
- 26 July 2012
- Proposed online date
- August 2007
- Withdrawn
- July 2012
Location
Marker shows the centre of Blue Earth County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Blue Earth County
- Solar project J4017, Blue Earth CountySolar Β· 299 MW Β· in study
- Battery storage project J4087, Blue Earth CountyBattery storage Β· 183 MW Β· in study
- Gas project G261, Blue Earth CountyGas Β· 667 MW Β· built
- Gas project J299, Blue Earth CountyGas Β· 73.0 MW Β· built
- Gas project G407, Blue Earth CountyGas Β· 667 MW Β· withdrawn
- Gas project J073, Blue Earth CountyGas Β· 194 MW Β· withdrawn
- Onshore wind project G828, Blue Earth CountyOnshore wind Β· 76.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem