United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

SOLAR Β· MISO

Solar project J547, Sherburne County

Solar project J547, Sherburne County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Sherburne County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2016 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J547
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Sherburne County, Minnesota
Technology
Solar: 100 MW
Total requested
100 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
14 March 2016
Proposed online date
August 2018
Withdrawn
July 2017

Location

Marker shows the centre of Sherburne County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Sherburne County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem