COAL Β· MISOCoal project G169, Sherburne County
Coal project G169, Sherburne County is a 120 MW coal request withdrawn in the MISO interconnection queue, in Sherburne County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2002 (completed)
- Withdrawn / abandonedMar 2003 (project stopped here)
- ConsentedMar 2003 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G169
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Unknown
- Location
- Sherburne County, Minnesota
- Technology
- Coal: 120 MW
- Total requested
- 120 MW
- Queue status
- Withdrawn
- Entered queue
- 15 January 2002
- Agreement signed
- 25 March 2003
- Withdrawn
- March 2003
Location
Marker shows the centre of Sherburne County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Sherburne County
- Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2Other Β· 710 MW Β· in study
- Sherco South BESSBattery storage Β· 314 MW Β· in study
- Gas project J3289, Sherburne CountyGas Β· 235 MW Β· in study
- Solar project J1605, Sherburne CountySolar Β· 200 MW Β· in study
- Solar project J3439, Sherburne CountySolar Β· 100 MW Β· in study
- Gas project G389, Sherburne CountyGas Β· 200 MW Β· built
- Coal project G930, Sherburne CountyCoal Β· 60.0 MW Β· built
- Solar project J1337, Sherburne CountySolar Β· 300 MW Β· withdrawn
- Solar project J1531, Sherburne CountySolar Β· 200 MW Β· withdrawn
- Gas project G390, Sherburne CountyGas Β· 100 MW Β· withdrawn
- Solar project J349, Sherburne CountySolar Β· 100 MW Β· withdrawn
- Solar project J547, Sherburne CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem