SOLAR Β· MISOSolar project J1212, Murray County
Solar project J1212, Murray County is a 60.0 MW solar request withdrawn in the MISO interconnection queue, in Murray County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1212
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- NORTHERN STATES POWER COMPANY
- Connection point (POI)
- Chanarambie-Ellsborough 115kV Line
- Location
- Murray County, Minnesota
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 27 April 2019
- Proposed online date
- October 2023
- Withdrawn
- March 2021
Location
Marker shows the centre of Murray County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Murray County
- Solar project J874, Murray CountySolar Β· 150 MW Β· under construction
- Battery storage project J1045, Murray CountyBattery storage Β· 20.0 MW Β· under construction
- Onshore wind project J2104, Murray CountyOnshore wind Β· 230 MW Β· in study
- Onshore wind project J2447, Murray CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J2346, Murray CountyOnshore wind Β· 200 MW Β· in study
- Solar project J2309, Murray CountySolar Β· 100 MW Β· in study
- Onshore wind project G060, Murray CountyOnshore wind Β· 100 MW Β· built
- Onshore wind project G057, Murray CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project G037, Murray CountyOnshore wind Β· 36.0 MW Β· built
- Onshore wind project G272, Murray CountyOnshore wind Β· 10.0 MW Β· built
- Onshore wind project G252, Murray CountyOnshore wind Β· 10.0 MW Β· built
- Onshore wind project G492, Murray CountyOnshore wind Β· 5.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem