United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
SOLAR + STORAGE Β· MISOSolar + storage project J2760, Hubbard County
Solar + storage project J2760, Hubbard County is a 68.0 MW solar + storage request withdrawn in the MISO interconnection queue, in Hubbard County, Minnesota, connecting to MINNESOTA POWER INC..
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedOct 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J2760
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MINNESOTA POWER INC.
- Connection point (POI)
- BADOURA4 (608610) 230 kV Substation
- Location
- Hubbard County, Minnesota
- Technology
- Solar: 68.0 MW Β· Battery
- Total requested
- 68.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 15 September 2022
- Proposed online date
- June 2027
- Withdrawn
- October 2025
Location
Marker shows the centre of Hubbard County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Hubbard County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem