ONSHORE WIND Β· MISOOnshore wind project G875, Kittson County
Onshore wind project G875, Kittson County is a 80.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Kittson County, Minnesota.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2007 (completed)
- Withdrawn / abandonedFeb 2013 (project stopped here)
- ConsentedMar 2011 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G875
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Donaldson - Warsaw 115 kV
- Location
- Kittson County, Minnesota
- Technology
- Wind: 80.0 MW
- Total requested
- 80.0 MW
- Study phase
- Network Upgrade
- Queue status
- Withdrawn
- Entered queue
- 9 October 2007
- Agreement signed
- 25 March 2011
- Proposed online date
- March 2015
- Withdrawn
- February 2013
Location
Marker shows the centre of Kittson County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Kittson County
- Onshore wind project J3370, Kittson CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project J612, Kittson CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project J951, Kittson CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project G873, Kittson CountyOnshore wind Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem