United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
ONSHORE WIND Β· MISOOnshore wind project J3370, Kittson County
Onshore wind project J3370, Kittson County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Kittson County, Minnesota, connecting to OTTER TAIL POWER COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J3370
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- OTTER TAIL POWER COMPANY
- Connection point (POI)
- Other_
- Location
- Kittson County, Minnesota
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Withdrawn
- Entered queue
- 18 April 2024
- Proposed online date
- September 2028
- Withdrawn
- August 2025
Location
Marker shows the centre of Kittson County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Kittson County
- Onshore wind project J612, Kittson CountyOnshore wind Β· 150 MW Β· withdrawn
- Onshore wind project G875, Kittson CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project J951, Kittson CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Onshore wind project G873, Kittson CountyOnshore wind Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem