Onshore wind project J3370, Kittson County

Onshore wind project J3370, Kittson County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Kittson County, Minnesota, connecting to OTTER TAIL POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3370
Grid region
MISO (Midcontinent)
Utility / transmission owner
OTTER TAIL POWER COMPANY
Connection point (POI)
Other_
Location
Kittson County, Minnesota
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
September 2028
Withdrawn
August 2025

Location

Marker shows the centre of Kittson County; the queue data does not give exact sites.