ONSHORE WIND Β· MISO

Onshore wind project J612, Kittson County

Onshore wind project J612, Kittson County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Kittson County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJun 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J612
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Kittson County, Minnesota
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
9 May 2016
Proposed online date
September 2018
Withdrawn
June 2017

Location

Marker shows the centre of Kittson County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Kittson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem