Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown635117.0 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

635 requests ยท page 5 of 13
ProjectCapacityStatusLocationRegionQueuedOnline
Ramsey Storage
Battery storage ยท Hecate Energy Ramsey Storage LLC
201 MWAgreement signed Wharton, TXERCOT May 2020target 2027
Elbus BESS
Battery storage ยท BRP Elbus BESS LLC
201 MWIn study Caldwell, TXERCOT Dec 2020target 2028
Clutch City Solar Phase I
Solar ยท HZ Solar I, LLC
201 MWAgreement signed Brazoria, TXERCOT Jan 2020target 2028
Battery storage project GEN-2020-081, Rusk County
Battery storage
200 MWAgreement signed Rusk, TXSPP Apr 2020target 2028
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Solar project BHCT G29, Pueblo County
Solar ยท 174 Power Global
200 MWPaused / redesign Pueblo, COWest Aug 2020target 2023
Solar project J1616, Knox County
Solar
200 MWIn study Knox, INMISO Jun 2020target 2026
Solar project J1691, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Solar project 445, Moore County
Solar
200 MWAgreement signed Moore, TNSoutheast Jun 2020target 2025
Solar project 423, Clay County
Solar
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2026
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Onshore wind project J1831, Menard County
Onshore wind
200 MWIn study Menard, ILMISO Jun 2020target 2026
Battery storage project 87, Skagit County
Battery storage
200 MWAgreement signed Skagit, WAWest Jul 2020target 2028
Solar project J1525, Huron County
Solar
200 MWAgreement signed Huron, MIMISO Jun 2020target 2026
Solar project J1808, Barron County
Solar
200 MWIn study Barron, WIMISO Jun 2020target 2026
Solar project G0655, Lake County
Solar
200 MWIn study Lake, ORWest Aug 2020target 2027
Solar project J1772, White County
Solar
200 MWIn study White, INMISO Jun 2020target 2026
Solar + storage project Q355, Maricopa County
Solar + storage
200 MWPaused / redesign Maricopa, AZWest Sep 2020target 2023
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Solar project J1780, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2020target 2026
Solar project J1664, St. Clair County
Solar
200 MWAgreement signed St. Clair, MIMISO Jun 2020target 2026
Solar project 7, Grant County
Solar
200 MWIn study Grant, WAWest Sep 2020
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J1559, Conway County
Solar
200 MWUnder construction Conway, ARMISO Jun 2020target 2026
Solar project J1605, Sherburne County
Solar
200 MWIn study Sherburne, MNMISO Jun 2020target 2026
Solar project J1550, Branch County
Solar
200 MWAgreement signed Branch, MIMISO Jun 2020target 2025
Steward Creek Solar
Solar ยท Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Mar 2020target 2023
Stem Solar
Solar ยท Innovative Solar 134, LLC
200 MWIn study Swisher, TXERCOT Feb 2020target 2025
Solar project J1562, Mississippi County
Solar
200 MWAgreement signed Mississippi, ARMISO Jun 2020target 2025
Prairie Creek Wind
Onshore wind ยท Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Battery storage project GEN-2020-060, Lubbock County
Battery storage
200 MWIn study Lubbock, TXSPP Apr 2020target 2027
Solar + storage project Company 192, Clark County
Solar + storage
200 MWAgreement signed Clark, NVWest Sep 2020target 2024
Solar project J1558, Pope County
Solar
200 MWIn study Pope, ARMISO Jun 2020target 2026
Solar project IC-868, Bartow County
Solar
200 MWAgreement signed Bartow, GASoutheast May 2020target 2028
Battery storage project 429, Clay County
Battery storage
200 MWAgreement signed Clay, MSSoutheast Apr 2020target 2028
Other project 77, Apache County
Other
200 MWIn study Apache, AZWest Feb 2020target 2023
Solar + storage project CSU-2020-3, El Paso County
Solar + storage
200 MWIn study El Paso, COWest Jun 2020target 2025
Teays River Wind Farm
Onshore wind ยท Teays River Wind Farm LLC f/k/a Blackford County Wind Farm LLC
200 MWIn study Blackford, INPJM Mar 2020target 2023
Solar project J1786, Sullivan County
Solar
200 MWIn study Sullivan, INMISO Jun 2020target 2026
Cass County Solar
Solar + storage ยท Steelhead Solar, LLC
200 MWIn study Cass, MIPJM Mar 2020target 2023
Riverbank Energy
Battery storage ยท Lincoln Reserve Energy, LLC
200 MWIn study Cook, ILPJM Mar 2020target 2024
Solar project J1673, Sabine Parish County
Solar
200 MWIn study Sabine Parish, LAMISO Jun 2020target 2025
Solar project G0645, Klickitat County
Solar
200 MWIn study Klickitat, WAWest Mar 2020target 2026
Solar project J1519, Bollinger County
Solar
200 MWIn study Bollinger, MOMISO Jun 2020target 2025
Flat Creek Solar
Solar ยท Flat Creek Solar NY LLC
200 MWIn study Montgomery, NYNYISO Sep 2020target 2028
Solar + storage project Q333, Navajo County
Solar + storage
200 MWIn study Navajo, AZWest Mar 2020target 2024
Solar project GI-2020-01, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Solar project GI-2020-03, Pueblo County
Solar
199 MWPaused / redesign Pueblo, COWest Mar 2020target 2023
Accalia Point Solar
Solar ยท Accalia Point Solar LLC
191 MWIn study Cameron, TXERCOT Oct 2020target 2029
Battery storage project G0637, Klickitat County
Battery storage
190 MWIn study Klickitat, WAWest Jan 2020target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)