United States › Grid › Interconnection queues › Missouri

SOLAR · MISO

Solar project J1519, Bollinger County

Solar project J1519, Bollinger County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Bollinger County, Missouri, connecting to AMEREN MISSOURI.

Queue statusIn planning
  1. PlanningQueued Jun 2020 (current stage)
  2. ConsentedJun 2025 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1519
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN MISSOURI
Connection point (POI)
St. Francois to Lutesville 345 kV
Location
Bollinger County, Missouri
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
18 June 2020
Agreement signed
19 June 2025
Proposed online date
December 2025

Location

Marker shows the centre of Bollinger County; the queue data does not give exact sites.