Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 411 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q117, Maricopa County
Solar
18.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Wind
Onshore wind
18.0 MWWithdrawn / abandoned Coos, NHISO-NE Apr 2013target 2017
Onshore wind project Q05, Fulton County
Onshore wind
18.0 MWWithdrawn / abandoned Fulton, PAPJM Feb 2006target 2008
Solar project W4-062, Burlington County
Solar
18.0 MWWithdrawn / abandoned Burlington, NJPJM Jan 2011target 2012
Battery storage project AE2-207, Edgecombe County
Battery storage
18.0 MWWithdrawn / abandoned Edgecombe, NCPJM Mar 2019target 2020
Offshore wind project Z1-035
Offshore wind
18.0 MWWithdrawn / abandoned OHPJM Jul 2013target 2017
Suny Fabius - Transmission Connected Solar PV Project
Solar · ABUNDANT SOLAR POWER (US-NY-MARKHAM HOLLOW RD-001) LLC
18.0 MWWithdrawn / abandoned Onondaga, NYNYISO Nov 2022
Gas project AH1-228, Fauquier County
Gas
18.0 MWWithdrawn / abandoned Fauquier, VAPJM Sep 2021target 2024
Other project S64, York County
Other
18.0 MWWithdrawn / abandoned York, PAPJM Jul 2007target 2011
Onshore wind project G969, Benton County
Onshore wind
18.0 MWWithdrawn / abandoned Benton, INMISO Feb 2008target 2010
Solar project W1-090, Camden County
Solar
18.0 MWWithdrawn / abandoned Camden, NJPJM Apr 2010target 2011
Cross Trails Gravitational Storage
Other · Cross Trails Energy Storage Project, LLC
18.0 MWWithdrawn / abandoned Scurry, TXERCOT May 2022target 2025
Onshore wind project Q06, Fulton County
Onshore wind
18.0 MWWithdrawn / abandoned Fulton, PAPJM Feb 2006target 2008
Solar project 957076, Newberry County
Solar
18.0 MWWithdrawn / abandoned Newberry, SCSoutheast Jun 2024
Eden Evans Rd
Solar · Solar Liberty Energy Systems, Inc.
18.0 MWWithdrawn / abandoned Erie, NYNYISO Sep 2017
South Mountain Wind
Onshore wind · South Mountain Wind, LLC
18.0 MWWithdrawn / abandoned Delaware, NYNYISO Oct 2011
Gas project AC1-011, Clarion County
Gas
18.0 MWWithdrawn / abandoned Clarion, PAPJM Jun 2016target 2018
Penn Wind
Onshore wind
18.0 MWWithdrawn / abandoned Northumberland, PAPJM May 2007target 2013
Kernridge Expansion
Solar
17.9 MWWithdrawn / abandoned Kern, CACAISO May 2018target 2020
Giffen 1
Solar
17.9 MWWithdrawn / abandoned Fresno, CACAISO Mar 2011target 2014
Bio Verde PV - Kettleman 2
Solar
17.8 MWWithdrawn / abandoned Kings, CACAISO Feb 2010target 2012
Solar project X3-053, Medina County
Solar
17.7 MWWithdrawn / abandoned Medina, OHPJM Sep 2011target 2013
Solar project IC-1209, Mcduffie County
Solar
17.6 MWWithdrawn / abandoned Mcduffie, GASoutheast Dec 2023target 2025
Snyder BESS
Other · Snyder Wind Farm, LLC
17.6 MWWithdrawn / abandoned Scurry, TXERCOT Mar 2019target 2021
Hornell Center 16
Solar · Sky Solar Inc.
17.6 MWWithdrawn / abandoned Allegany, NYNYISO Jun 2019
Other project 98, Gem County
Other
17.5 MWWithdrawn / abandoned Gem, IDWest Oct 2003target 2008
Onshore wind project J005, Todd County
Onshore wind
17.5 MWWithdrawn / abandoned Todd, MNMISO Oct 2008target 2009
Solar project Q231, Cochise County
Solar
17.5 MWWithdrawn / abandoned Cochise, AZWest Oct 2015target 2016
Solar project AG2-512, Marion County
Solar
17.5 MWWithdrawn / abandoned Marion, KYPJM Mar 2021target 2023
Solar + storage project AG1-084, Hertford County
Solar + storage
17.5 MWWithdrawn / abandoned Hertford, NCPJM Jul 2020target 2021
Findlay Solar Park
Solar + storage
17.5 MWWithdrawn / abandoned Allegheny, PAPJM Jul 2020target 2025
Pembroke Solar
Solar
17.5 MWWithdrawn / abandoned Merrimack, NHISO-NE Oct 2019target 2024
Solar + storage project AG1-085, Hertford County
Solar + storage
17.5 MWWithdrawn / abandoned Hertford, NCPJM Jul 2020target 2021
Solar project AC2-163, Middlesex County
Solar
17.5 MWWithdrawn / abandoned Middlesex, VAPJM Mar 2017target 2019
Group @ Medway 65 - EMA ASO
Solar + storage
17.5 MWWithdrawn / abandoned Middlesex, MAISO-NE Jan 2022target 2023
wind
Onshore wind
17.4 MWWithdrawn / abandoned Franklin, VTISO-NE Feb 2015target 2016
Alden Energy Storage Project
Battery storage · SATURN ENERGY STORAGE
17.3 MWWithdrawn / abandoned Erie, NYNYISO Mar 2023
Onshore wind project 50, Lewis County
Onshore wind
17.3 MWWithdrawn / abandoned Lewis, WAWest Jun 2017target 2018
Solar project IC-365, Candler County
Solar
17.3 MWWithdrawn / abandoned Candler, GASoutheast Apr 2014
Gas project AB1-117, Fluvanna County
Gas
17.3 MWWithdrawn / abandoned Fluvanna, VAPJM Oct 2015target 2016
Solar
Solar
17.2 MWWithdrawn / abandoned Sagadahoc, MEISO-NE Apr 2020target 2030
Gas project AF1-072, Kane County
Gas
17.2 MWWithdrawn / abandoned Kane, ILPJM Aug 2019target 2019
Alden Energy Storage Project
Battery storage · Saturn Energy Storage
17.1 MWWithdrawn / abandoned Erie, NYNYISO Jul 2023
Solar project X1-089, Warren County
Solar
17.0 MWWithdrawn / abandoned Warren, NJPJM Apr 2011target 2012
South Main Street Solar Farm
Solar
17.0 MWWithdrawn / abandoned Warren, NJPJM Sep 2010target 2014
Dexter Solar
Solar · Enel Green Power North America
17.0 MWWithdrawn / abandoned Jefferson, NYNYISO Jul 2012
Other project 114, Taylor County
Other · Masked
17.0 MWWithdrawn / abandoned Taylor, FLSoutheast Sep 2011
Belcher Solar
Solar
17.0 MWWithdrawn / abandoned Louisa, VAPJM Sep 2018target 2021
Solar project AD2-041, Whiteside County
Solar
17.0 MWWithdrawn / abandoned Whiteside, ILPJM Jan 2018target 2019
Solar project AH1-069, Ashland County
Solar · JR ME LLC
17.0 MWWithdrawn / abandoned Ashland, OHPJM Mar 2025target 2023
Page 411 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)