United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR Β· NYISOEden Evans Rd
Eden Evans Rd is a 18.0 MW solar request withdrawn in the NYISO interconnection queue, in Erie County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2017 (completed)
- Withdrawn / abandonedMar 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 661
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Solar Liberty Energy Systems, Inc.
- Connection point (POI)
- Shelton - Angola 34.5kV
- Location
- Erie County, New York
- Technology
- Solar: 18.0 MW
- Total requested
- 18.0 MW
- Queue status
- Withdrawn
- Entered queue
- 7 September 2017
- Withdrawn
- March 2018
Location
Marker shows the centre of Erie County; the queue data does not give exact sites.
Other requests in Erie County
- Levy Grid, LLCBattery storage Β· 150 MW Β· in study
- Kce NY 10Battery storage Β· 20.0 MW Β· in study
- Kce NY 6Battery storage Β· 20.0 MW Β· built
- Kce NY 6Battery storage Β· 20.0 MW Β· built
- Steel Winds IIOnshore wind Β· 15.0 MW Β· built
- Steel Winds IIOnshore wind Β· 15.0 MW Β· built
- Huntley Energy StorageBattery storage Β· 300 MW Β· withdrawn
- CWW 300 WindOnshore wind Β· 300 MW Β· withdrawn
- Genesee Road Solar Energy CenterSolar Β· 250 MW Β· withdrawn
- River Road StorageBattery storage Β· 250 MW Β· withdrawn
- River Road Energy StorageBattery storage Β· 248 MW Β· withdrawn
- CWW 200 WindOnshore wind Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem