🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Kce NY 10

Kce NY 10 is a 20.0 MW battery storage request in interconnection study in the NYISO interconnection queue, in Erie County, New York, connecting to NYSEG.

Queue statusIn planning
  1. PlanningQueued Mar 2019 (current stage)
  2. ConsentedOct 2022 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
804
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
KCE NY 10, LLC
Connection point (POI)
Erie Substation 34.5kV
Location
Erie County, New York
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Study phase
FES, SIS, FS
Queue status
Active
Entered queue
22 March 2019
Agreement signed
20 October 2022
Proposed online date
October 2026

Location

Marker shows the centre of Erie County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Erie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem