United States › Grid › Interconnection queues › New York
SOLAR · NYISOSuny Fabius - Transmission Connected Solar PV Project
Suny Fabius - Transmission Connected Solar PV Project is a 18.0 MW solar request withdrawn in the NYISO interconnection queue, in Onondaga County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1470
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- ABUNDANT SOLAR POWER (US-NY-MARKHAM HOLLOW RD-001) LLC
- Connection point (POI)
- Tilden - Cortland 18 115kV
- Location
- Onondaga County, New York
- Technology
- Solar: 18.0 MW
- Total requested
- 18.0 MW
- Queue status
- Withdrawn
- Entered queue
- 18 November 2022
Location
Marker shows the centre of Onondaga County; the queue data does not give exact sites.
Other requests in Onondaga County
- Maple Harvest WindOnshore wind · 162 MW · in study
- Sky High SolarSolar · 20.0 MW · in study
- Mill Run BESSBattery storage · 260 MW · withdrawn
- Icebox Energy StorageBattery storage · 202 MW · withdrawn
- Cassiopeia Energy CenterBattery storage · 200 MW · withdrawn
- Gillie Brook SolarSolar · 200 MW · withdrawn
- ELP Clay StorageBattery storage · 199 MW · withdrawn
- ELP Clay StorageBattery storage · 165 MW · withdrawn
- Zenith BESSBattery storage · 165 MW · withdrawn
- Eastwater Energy StorageBattery storage · 101 MW · withdrawn
- Three Rivers Energy StorageBattery storage · 80.0 MW · withdrawn
- Syracuse Energy StorageBattery storage · 79.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem