BATTERY STORAGE · NYISO

Eastwater Energy Storage

Eastwater Energy Storage is a 101 MW battery storage request withdrawn in the NYISO interconnection queue, in Onondaga County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1605
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Grid Connected Infrastructure, LLC
Connection point (POI)
Mortimer 115 kV Bus
Location
Onondaga County, New York
Technology
Battery: 101 MW
Total requested
101 MW
Queue status
Withdrawn
Entered queue
7 September 2023
Withdrawn
November 2023

Location

Marker shows the centre of Onondaga County; the queue data does not give exact sites.