ELP Clay Storage

ELP Clay Storage is a 165 MW battery storage request withdrawn in the NYISO interconnection queue, in Onondaga County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1525
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
ELP Clay Storage LLC
Connection point (POI)
115 kV Line #7 Clay-Lighthouse Hill
Location
Onondaga County, New York
Technology
Battery: 165 MW
Total requested
165 MW
Queue status
Withdrawn
Entered queue
24 February 2023

Location

Marker shows the centre of Onondaga County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Onondaga County