United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR Β· PJM

Solar project X3-053, Medina County

Solar project X3-053, Medina County is a 17.7 MW solar request withdrawn in the PJM interconnection queue, in Medina County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2011 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
X3-053
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Homer-Seville 69kV
Location
Medina County, Ohio
Technology
Solar: 17.7 MW
Total requested
17.7 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
29 September 2011
Proposed online date
July 2013
Withdrawn
August 2012

Location

Marker shows the centre of Medina County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem