United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMSolar project X3-053, Medina County
Solar project X3-053, Medina County is a 17.7 MW solar request withdrawn in the PJM interconnection queue, in Medina County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2011 (completed)
- Withdrawn / abandonedAug 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- X3-053
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Homer-Seville 69kV
- Location
- Medina County, Ohio
- Technology
- Solar: 17.7 MW
- Total requested
- 17.7 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 29 September 2011
- Proposed online date
- July 2013
- Withdrawn
- August 2012
Location
Marker shows the centre of Medina County; the queue data does not give exact sites.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem