United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

OFFSHORE WIND Β· PJM

Offshore wind project Z1-035

Offshore wind project Z1-035 is a 18.0 MW offshore wind request withdrawn in the PJM interconnection queue, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2013 (completed)
  2. Withdrawn / abandonedFeb 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Z1-035
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Connection point (POI)
Lake Road 11.5 kV
Location
Ohio
Technology
Offshore Wind: 18.0 MW
Total requested
18.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Withdrawn
Queue status
Withdrawn
Entered queue
5 July 2013
Proposed online date
September 2017
Withdrawn
February 2022

Location

No county location in the queue data.

Power plants in Ohio Β· Transmission lines in Ohio

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem