Withdrawn queue requests in the USA (2018 requests) โ€” page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests ยท page 4 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Azure Sky Wind 1
Onshore wind ยท Tradewind Energy
350 MWWithdrawn / abandoned Throckmorton, TXERCOT Jun 2018target 2020
Solar project 119, Dorchester County
Solar
350 MWWithdrawn / abandoned Dorchester, SCSoutheast Dec 2018target 2021
Gusty Hill Wind
Onshore wind ยท Gusty Hill Wind Project, LLC
350 MWWithdrawn / abandoned Culberson, TXERCOT Jun 2018target 2022
Solar project 353, Fayette County
Solar
340 MWWithdrawn / abandoned Fayette, TNSoutheast Jun 2018
Elrond
Solar ยท IP Elrond, LLC
313 MWWithdrawn / abandoned Haskell, TXERCOT Sep 2018target 2021
Lumina Solar
Solar ยท IP Lumina, LLC
313 MWWithdrawn / abandoned Scurry, TXERCOT Sep 2018target 2022
Silverwing
Solar + storage
312 MWWithdrawn / abandoned Riverside, CACAISO Apr 2018target 2022
Onshore wind project GEN-2018-032, Mcpherson County
Onshore wind
310 MWWithdrawn / abandoned Mcpherson, KSSPP May 2018target 2029
Solar project AE1-089, St. Joseph County
Solar
310 MWWithdrawn / abandoned St. Joseph, INPJM Aug 2018target 2021
Key Storage 2
Battery storage
309 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2024
Other project AD2-080, St. Joseph County
Other
309 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2018target 2020
Casy Solar
Solar + storage
308 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Onshore wind project G0595, Lewis County
Onshore wind
307 MWWithdrawn / abandoned Lewis, WAWest Jul 2018target 2022
Solar project GEN-2018-118, Lea County
Solar
305 MWWithdrawn / abandoned Lea, NMSPP Nov 2018target 2021
Great Dane Wind
Onshore wind ยท Seventus
303 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2018target 2020
Onshore wind project GEN-2018-068, Madison County
Onshore wind
302 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Onshore wind project AE1-211, Jasper County
Onshore wind
302 MWWithdrawn / abandoned Jasper, INPJM Sep 2018target 2020
Onshore wind project GEN-2018-017, Keith County
Onshore wind
302 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Solar project AE1-133, Alamance County
Solar
300 MWWithdrawn / abandoned Alamance, NCPJM Sep 2018target 2022
Solar project J1095, Desoto County
Solar
300 MWWithdrawn / abandoned Desoto, MSMISO Mar 2018target 2021
Solar project GI-74, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Onshore wind project AD2-142, Will County
Onshore wind
300 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Solar project GI-72, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Nov 2018target 2021
Solar project 534, Jerome County
Solar
300 MWWithdrawn / abandoned Jerome, IDWest May 2018
Solar project GI-76, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Solar project GI-73, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project J1085, Marathon County
Onshore wind
300 MWWithdrawn / abandoned Marathon, WIMISO Mar 2018target 2021
Onshore wind project GEN-2018-042, Johnson County
Onshore wind
300 MWWithdrawn / abandoned Johnson, NESPP May 20182025
Solar + storage project Company JM, Humboldt County
Solar + storage
300 MWWithdrawn / abandoned Humboldt, NVWest Sep 2018target 2021
Solar project AE1-047, Spotsylvania County
Solar
300 MWWithdrawn / abandoned Spotsylvania, VAPJM Jul 2018target 2021
Solar project J1073, Iberville Parish County
Solar
300 MWWithdrawn / abandoned Iberville Parish, LAMISO Mar 2018target 2021
Solar + storage project 64, Pima County
Solar + storage
300 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2021
Solar project J1053, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, WIMISO Mar 2018target 2021
Solar project GEN-2018-022, Nodaway County
Solar
300 MWWithdrawn / abandoned Nodaway, MOSPP May 20182025
Onshore wind project J1081, Polk County
Onshore wind
300 MWWithdrawn / abandoned Polk, MNMISO Mar 2018target 2020
Atlantic Shores Offshore Wind Project 1
Offshore wind
300 MWWithdrawn / abandoned Atlantic, NJPJM Dec 2018target 2029
Battery storage project Company JA, Washoe County
Battery storage
300 MWWithdrawn / abandoned Washoe, NVWest Sep 2018target 2020
Solar project GI-75, New Madrid County
Solar
300 MWWithdrawn / abandoned New Madrid, MOSoutheast Dec 2018target 2021
Fort McKavett Wind
Onshore wind ยท Nextera
300 MWWithdrawn / abandoned Menard, TXERCOT Aug 2018target 2020
Mavericks
Battery storage
300 MWWithdrawn / abandoned Alameda, CACAISO Apr 2018target 2021
Solar project 1049, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Solar project 1050, Utah County
Solar
300 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2020
Tiger Wind
Onshore wind ยท Nextera
300 MWWithdrawn / abandoned Taylor, TXERCOT Oct 2018target 2022
Onshore wind project J977, Jackson County
Onshore wind
300 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Solar project GI-70, Pemiscot County
Solar
300 MWWithdrawn / abandoned Pemiscot, MOSoutheast Nov 2018target 2021
Onshore wind project J1177, Schuyler County
Onshore wind
300 MWWithdrawn / abandoned Schuyler, MOMISO Mar 2018target 2020
Callisto
Solar ยท Intersect Power
300 MWWithdrawn / abandoned Borden, TXERCOT Apr 2018target 2021
Onshore wind project GEN-2018-047, Ellsworth County
Onshore wind
300 MWWithdrawn / abandoned Ellsworth, KSSPP May 2018target 2021
Onshore wind project GI-2018-26, Kit Carson County
Onshore wind
300 MWWithdrawn / abandoned Kit Carson, COWest Aug 2018target 2020
Solar project J1078, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)