BATTERY STORAGE Β· CAISO

Mavericks

Mavericks is a 300 MW battery storage request withdrawn in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2018 (completed)
  2. Withdrawn / abandonedFeb 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1502
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Newark Station 230kV
Location
Alameda County, California
Technology
Battery: 300 MW
Total requested
300 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
16 April 2018
Proposed online date
July 2021
Withdrawn
February 2019

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem