ONSHORE WIND Β· SPP

Onshore wind project GEN-2018-032, Mcpherson County

Onshore wind project GEN-2018-032, Mcpherson County is a 310 MW onshore wind request withdrawn in the SPP interconnection queue, in Mcpherson County, Kansas, connecting to WERE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-032
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WERE
Connection point (POI)
Neosho 345kV Substation
Location
Mcpherson County, Kansas
Technology
Wind: 310 MW
Total requested
310 MW
Service type
Energy only (ERIS)
Study phase
TERMINATED
Queue status
Withdrawn
Entered queue
29 May 2018
Proposed online date
May 2029

Location

Marker shows the centre of Mcpherson County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Mcpherson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem