πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

GAS Β· SPP

Gas project GEN-2024-047, Mcpherson County

Gas project GEN-2024-047, Mcpherson County is a 124 MW gas request withdrawn in the SPP interconnection queue, in Mcpherson County, Kansas, connecting to Evergy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2024 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-047
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
Evergy
Connection point (POI)
Johns-Manville 115 kV Substation
Location
Mcpherson County, Kansas
Technology
Gas: 124 MW
Total requested
124 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 October 2024
Proposed online date
June 2031
Withdrawn
July 2025

Location

Marker shows the centre of Mcpherson County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Mcpherson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem