United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in West (non-ISO utilities) — page 34

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,857519.1 GW
Active in queue519.1 GW1,857 requests
Agreement signed60.6 GW349 requests
Withdrawn5,277949.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,857 requests · page 34 of 38
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IA-PNM-2012-04, Guadalupe Cty County
Solar
40.0 MWAgreement signed Guadalupe Cty, NMWest Aug 2012target 2016
Solar project CS24-14, Spokane County
Solar
40.0 MWAgreement signed Spokane, WAWest Apr 2024target 2028
Solar project CS23-13, Lincoln County
Solar
40.0 MWAgreement signed Lincoln, WAWest May 2023target 2028
Coal project BHBE G3, Campbell County
Coal · Basin Electric
40.0 MWAgreement signed Campbell, SDWest Aug 2004target 2011
Solar project CS23-14, Spokane County
Solar
40.0 MWAgreement signed Spokane, WAWest Apr 2023target 2028
Solar project 103, Lincoln County
Solar
40.0 MWIn study Lincoln, WAWest Dec 2019target 2021
Geothermal project Company LT, Lander County
Geothermal
40.0 MWAgreement signed Lander, NVWest Sep 2021target 2026
Solar + storage project TCS-54, Crook County
Solar + storage · SSEV C LLC
40.0 MWAgreement signed Crook, ORWest Apr 2020target 2026
Gas project 38777, Laramie County
Gas · Cheyenne Light, Fuel and Power Company
40.0 MWIn study Laramie, WYWest Jul 2025target 2026
Solar + storage project TCS-43, Crook County
Solar + storage · Three Springs Interconnection A LLC
40.0 MWAgreement signed Crook, ORWest Sep 2019target 2027
Geothermal project C2-179, Millard County
Geothermal · FEC Development LLC
40.0 MWPaused / redesign Millard, UTWest May 2022target 2029
Solar + storage project GI-2023-172, Imperial County
Solar + storage
39.2 MWIn study Imperial, CAWest Apr 2023target 2025
Geothermal project Company KJ, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2023
Geothermal project Company EV, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Apr 2010target 2026
Geothermal project 25-00389, Pershing County
Geothermal
38.5 MWIn study Pershing, NVWest Jul 2025target 2029
Geothermal project Company KI, Washoe County
Geothermal
38.5 MWAgreement signed Washoe, NVWest Feb 2020target 2025
Geothermal project Company QK, Lyon County
Geothermal
38.5 MWAgreement signed Lyon, NVWest Sep 2023target 2030
Geothermal project Company KH, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Feb 2020target 2022
Geothermal project 25-00391, Mineral County
Geothermal
38.5 MWIn study Mineral, NVWest Jul 2025target 2028
Geothermal project Company KG, Eureka County
Geothermal
38.5 MWAgreement signed Eureka, NVWest Feb 2020target 2027
Geothermal project Company KY, Esmeralda County
Geothermal
38.5 MWAgreement signed Esmeralda, NVWest Mar 2021target 2027
Geothermal project Company KZ, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Mar 2021target 2027
Geothermal project Company HU, Churchill County
Geothermal
38.5 MWAgreement signed Churchill, NVWest Sep 2017target 2023
Other project 11-042, Jefferson County
Other
37.0 MWPaused / redesign Jefferson, ORWest Jun 2011target 2013
Solar project GI-2017-52, El Paso County
Solar
36.0 MWAgreement signed El Paso, COWest Dec 20172019
Gas project 377, Silver Bow County
Gas
36.0 MWPaused / redesign Silver Bow, MTWest May 2020target 2022
Solar + storage project GI-2022-158, Imperial County
Solar + storage
35.0 MWIn study Imperial, CAWest Sep 2022target 2024
Gas project GI-2021-3, Weld County
Gas
35.0 MWAgreement signed Weld, COWest Mar 2021target 2021
Gas project GI-2025-179, Imperial County
Gas
34.8 MWIn study Imperial, CAWest Feb 2025target 2027
Solar project 443, Crook County
Solar · Ponderosa Solar, LLC
34.6 MWAgreement signed Crook, ORWest Oct 2012target 2020
Geothermal project GI-2023-177, Imperial County
Geothermal
33.0 MWIn study Imperial, CAWest Apr 2023target 2026
Geothermal project 25-00425, Pershing County
Geothermal
31.0 MWIn study Pershing, NVWest Jul 2025target 2030
Onshore wind project C2-13, Carbon County
Onshore wind · PacifiCorp
30.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Solar + storage project 556, Grant County
Solar + storage · Prairie City PV1, LLC
30.0 MWPaused / redesign Grant, ORWest Apr 2019target 2024
Gas project Q66, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Gas project Q81, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Jun 2021target 2025
Battery storage project G0733, Benton County
Battery storage
30.0 MWIn study Benton, WAWest Mar 2022target 2025
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012
Solar + storage project 783, Natrona County
Solar + storage · Dinosolar, LLC
30.0 MWAgreement signed Natrona, WYWest Aug 2016target 2024
Gas project 12-048, Morrow County
Gas
30.0 MWPaused / redesign Morrow, ORWest Feb 2012target 2012
Gas project Q65, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Nov 2020target 2022
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Onshore wind project PIS052, Carbon County
Onshore wind · PacifiCorp
30.0 MWIn study Carbon, WYWest Feb 2024target 2024
Geothermal project Company LR, Lander County
Geothermal
29.0 MWAgreement signed Lander, NVWest Sep 2021target 2024
Geothermal project IA-PNM-2015-01, Doña Ana Cty County
Geothermal · ORNI 24
29.0 MWAgreement signed Doña Ana Cty, NMWest Jul 2015target 2021
Geothermal project IA-PNM-2014-04, Dona Ana Cty County
Geothermal
29.0 MWIn study Dona Ana Cty, NMWest Mar 2014target 2018
Other project GI-2021-144, Imperial County
Other
28.0 MWIn study Imperial, CAWest Mar 2021target 2028
Onshore wind project C2-14, Carbon County
Onshore wind · PacifiCorp
28.0 MWAgreement signed Carbon, WYWest Apr 2022target 2036
Onshore wind project PIS053, Carbon County
Onshore wind · PacifiCorp
28.0 MWIn study Carbon, WYWest Feb 2024target 2024
Gas project G0620, Umatilla County
Gas
27.0 MWIn study Umatilla, ORWest Apr 2019target 2019
Page 34 of 38

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)