Gas project 377, Silver Bow County

Gas project 377, Silver Bow County is a 36.0 MW gas request suspended in the West interconnection queue, in Silver Bow County, Montana, connecting to NorthWestern Energy.

Queue statusPaused / redesign
  1. PlanningQueued May 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
377
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
161kV at MHD
Location
Silver Bow County, Montana
Technology
Gas: 36.0 MW
Total requested
36.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Suspended
Entered queue
7 May 2020
Proposed online date
July 2022

Location

Marker shows the centre of Silver Bow County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Silver Bow County