SOLAR + STORAGE Β· WEST

Solar + storage project 397, Silver Bow County

Solar + storage project 397, Silver Bow County is a 120 MW solar + storage request withdrawn in the West interconnection queue, in Silver Bow County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
397
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Asimi 161kV Substation
Location
Silver Bow County, Montana
Technology
Solar: 120 MW Β· Battery
Total requested
120 MW
Service type
NRIS and ERIS
Study phase
Feasiblity Study
Queue status
Withdrawn
Entered queue
30 September 2020
Proposed online date
November 2023

Location

Marker shows the centre of Silver Bow County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Silver Bow County