🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

GEOTHERMAL · WEST

Geothermal project Company KJ, Washoe County

Geothermal project Company KJ, Washoe County is a 38.5 MW geothermal request with a signed interconnection agreement in the West interconnection queue, in Washoe County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Feb 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company KJ
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Washoe County, Nevada
Technology
Geothermal: 38.5 MW
Total requested
38.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
28 February 2020
Proposed online date
January 2023

Location

Marker shows the centre of Washoe County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Washoe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem