Solar + storage project Company JI, Washoe County

Solar + storage project Company JI, Washoe County is a 400 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Washoe County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Sep 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company JI
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Washoe County, Nevada
Technology
Solar: 400 MW · Battery
Total requested
400 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
27 September 2018
Proposed online date
December 2023

Location

Marker shows the centre of Washoe County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Washoe County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem