United States › Grid › Interconnection queues › Oklahoma

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Oklahoma — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15838.1 GW
Active in queue52.5 GW240 requests
Agreement signed14.4 GW82 requests
Withdrawn467102.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

158 requests · page 3 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2022-235, Canadian County
Battery storage
150 MWIn study Canadian, OKSPP Feb 2023target 2028
Battery storage project GEN-2024-244, Texas County
Battery storage
150 MWIn study Texas, OKSPP Mar 2025target 2029
Battery storage project GEN-2023-057, Pawnee County
Battery storage
150 MWIn study Pawnee, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-238, Pottawatomie County
Battery storage
150 MWIn study Pottawatomie, OKSPP Feb 2023target 2028
Battery storage project GEN-2024-029, Logan County
Battery storage
150 MWIn study Logan, OKSPP Oct 2024target 2028
Battery storage project GEN-2022-017, Woodward County
Battery storage
150 MWIn study Woodward, OKSPP Jun 2022target 2028
Battery storage project GEN-2024-SR9, Beaver County
Battery storage
150 MWIn study Beaver, OKSPP Jan 2024target 2027
Battery storage project GEN-2024-332, Oklahoma County
Battery storage
150 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Solar + storage project GEN-2024-117, Washington County
Solar + storage
150 MWIn study Washington, OKSPP Mar 2025target 2028
Solar + storage project GEN-2024-362, Grady County
Solar + storage
140 MWIn study Grady, OKSPP Mar 2025target 2029
Solar project GEN-2024-157, Kiowa County
Solar
140 MWIn study Kiowa, OKSPP Mar 2025target 2029
Solar + storage project GEN-2020-010, Woodward County
Solar + storage
140 MWIn study Woodward, OKSPP Apr 2020target 2027
Gas project GEN-2024-286, Le Flore County
Gas
136 MWIn study Le Flore, OKSPP Mar 2025target 2031
Solar + storage project GEN-2023-063, Rogers County
Solar + storage
135 MWIn study Rogers, OKSPP Oct 2023target 2028
Other project GEN-2025-SR13, Seminole County
Other
130 MWIn study Seminole, OKSPP May 2025target 2029
Solar + storage project GEN-2023-092, Choctaw County
Solar + storage
125 MWIn study Choctaw, OKSPP Oct 2023target 2028
Other project GEN-2025-SR15, Mcclain County
Other
125 MWIn study Mcclain, OKSPP May 2025target 2029
Battery storage project GEN-2023-SR22, Mayes County
Battery storage
125 MWIn study Mayes, OKSPP Jun 20232024
Gas project GEN-2024-334, Kay County
Gas
124 MWIn study Kay, OKSPP Mar 2025target 2029
Battery storage project ERAS-2025-022, Pontotoc County
Battery storage
123 MWIn study Pontotoc, OKSPP Oct 2025target 2028
Battery storage project GEN-2023-SR20, Custer County
Battery storage
120 MWIn study Custer, OKSPP Jun 20232025
Solar project GEN-2024-056, Noble County
Solar
120 MWIn study Noble, OKSPP Oct 2024target 2029
Solar + storage project GEN-2024-373, Choctaw County
Solar + storage
120 MWIn study Choctaw, OKSPP Mar 2025target 2029
Onshore wind project GEN-2023-088, Okfuskee County
Onshore wind
117 MWIn study Okfuskee, OKSPP Oct 2023target 2028
Battery storage project GEN-2025-SR12, Noble County
Battery storage
116 MWIn study Noble, OKSPP May 2025target 2030
Solar project GEN-2022-104, Bryan County
Solar
113 MWIn study Bryan, OKSPP Jan 2023target 2028
Solar + storage project GEN-2020-012, Jackson County
Solar + storage
113 MWIn study Jackson, OKSPP Apr 2020target 2027
Battery storage project GEN-2025-SR11, Noble County
Battery storage
112 MWIn study Noble, OKSPP May 2025target 2030
Battery storage project GEN-2025-SR7, Muskogee County
Battery storage
102 MWIn study Muskogee, OKSPP May 2025target 2026
Battery storage project GEN-2023-SR27, Mayes County
Battery storage
102 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2024-333, Oklahoma County
Battery storage
100 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Battery storage project GEN-2024-SR16, Rogers County
Battery storage
100 MWIn study Rogers, OKSPP Dec 2024target 2026
Battery storage project GEN-2023-055, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-012, Woodward County
Battery storage
100 MWIn study Woodward, OKSPP Jun 2022target 2028
Battery storage project GEN-2022-154, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Feb 2023target 2027
Other project GEN-2025-SR19, Chouteau County
Other
100 MWIn study Chouteau, OKSPP Jun 2025target 2029
Solar + storage project GEN-2023-104, Woods County
Solar + storage
100 MWIn study Woods, OKSPP Oct 2023target 2028
Battery storage project GEN-2022-156, Creek County
Battery storage
100 MWIn study Creek, OKSPP Feb 2023target 2027
Solar + storage project GEN-2021-064, Caddo County
Solar + storage
100 MWIn study Caddo, OKSPP Apr 2021target 2028
Other project GEN-2025-SR23, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2026
Solar project GEN-2020-092, Mayes County
Solar
100 MWIn study Mayes, OKSPP Apr 2020target 2026
Other project GEN-2025-SR21, Tulsa County
Other
100 MWIn study Tulsa, OKSPP Jun 2025target 2028
Solar + storage project GEN-2023-069, Atoka County
Solar + storage
100 MWIn study Atoka, OKSPP Oct 2023target 2028
Battery storage project GEN-2024-180, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Mar 2025target 2029
Other project GEN-2025-SR22, Oklahoma County
Other
100 MWIn study Oklahoma, OKSPP Jun 2025target 2028
Battery storage project GEN-2021-088, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Apr 2021target 2027
Battery storage project GEN-2024-204, Bryan County
Battery storage
100 MWIn study Bryan, OKSPP Mar 2025target 2030
Solar project GEN-2022-071, Pittsburg County
Solar
90.8 MWIn study Pittsburg, OKSPP Aug 2022target 2028
Solar + storage project GEN-2024-361, Lincoln County
Solar + storage
80.0 MWIn study Lincoln, OKSPP Mar 2025target 2029
Battery storage project GEN-2023-161, Blaine County
Battery storage
74.9 MWIn study Blaine, OKSPP Oct 2023target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)