United States › Grid › Interconnection queues › Oklahoma
SOLAR + STORAGE · SPPSolar + storage project GEN-2020-012, Jackson County
Solar + storage project GEN-2020-012, Jackson County is a 113 MW solar + storage request in interconnection study in the SPP interconnection queue, in Jackson County, Oklahoma, connecting to AEP.
Queue statusIn planning
- PlanningQueued Apr 2020 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2020-012
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Snyder – Altus Jct. 138kV
- Location
- Jackson County, Oklahoma
- Technology
- Solar: 113 MW · Battery
- Total requested
- 113 MW
- Service type
- NRIS and ERIS
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 10 April 2020
- Proposed online date
- June 2027
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Solar project GEN-2024-158, Jackson CountySolar · 190 MW · in study
- Solar + storage project GEN-2024-161, Jackson CountySolar + storage · 170 MW · in study
- Solar project GEN-2022-003, Jackson CountySolar · 125 MW · withdrawn
- Solar project GEN-2015-085, Jackson CountySolar · 122 MW · withdrawn
- Solar project GEN-2024-086, Jackson CountySolar · 120 MW · withdrawn
- Solar + storage project GEN-2023-148, Jackson CountySolar + storage · 110 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem