🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Oklahoma

OTHER · SPP

Other project GEN-2025-SR13, Seminole County

Other project GEN-2025-SR13, Seminole County is a 130 MW other request in interconnection study in the SPP interconnection queue, in Seminole County, Oklahoma, connecting to OG&E.

Queue statusIn planning
  1. PlanningQueued May 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2025-SR13
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OG&E
Connection point (POI)
Seminole Substation
Location
Seminole County, Oklahoma
Technology
Other: 130 MW
Total requested
130 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
31 May 2025
Proposed online date
December 2029

Location

Marker shows the centre of Seminole County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Seminole County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem