United States › Grid › Interconnection queues › Oklahoma
OTHER · SPPOther project GEN-2025-SR13, Seminole County
Other project GEN-2025-SR13, Seminole County is a 130 MW other request in interconnection study in the SPP interconnection queue, in Seminole County, Oklahoma, connecting to OG&E.
Queue statusIn planning
- PlanningQueued May 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2025-SR13
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OG&E
- Connection point (POI)
- Seminole Substation
- Location
- Seminole County, Oklahoma
- Technology
- Other: 130 MW
- Total requested
- 130 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 31 May 2025
- Proposed online date
- December 2029
Location
Marker shows the centre of Seminole County; the queue data does not give exact sites.
Other requests in Seminole County
- Gas project GEN-2024-321, Seminole CountyGas · 493 MW · in study
- Other project GEN-2025-SR10, Seminole CountyOther · 238 MW · in study
- Solar + storage project GEN-2024-360, Seminole CountySolar + storage · 160 MW · in study
- Gas project GEN-2000-014, Seminole CountyGas · 1,300 MW · withdrawn
- Solar project GEN-2021-SR1, Seminole CountySolar · 81.6 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem