Interconnection queue in SPP (Southwest Power Pool) — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown692152.4 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

692 requests · page 3 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2024-316, Atoka County
Solar
300 MWIn study Atoka, OKSPP Mar 2025target 2030
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Onshore wind project GEN-2024-258, Allen County
Onshore wind
300 MWIn study Allen, KSSPP Mar 2025target 2030
Onshore wind project GEN-2024-137, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar project GEN-2024-078, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2018-048, Caddo County
Solar
300 MWAgreement signed Caddo, OKSPP May 2018target 2028
Gas project GEN-2024-254, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Solar project GEN-2024-099, Castro County
Solar
300 MWIn study Castro, TXSPP Mar 2025target 2031
Battery storage project GEN-2022-139, Harrison County
Battery storage
300 MWIn study Harrison, TXSPP Feb 2023target 2030
Solar + storage project GEN-2024-113, Sequoyah County
Solar + storage
300 MWIn study Sequoyah, OKSPP Mar 2025target 2028
Solar project GEN-2024-038, Nemaha County
Solar
300 MWIn study Nemaha, NESPP Oct 2024target 2029
Onshore wind project GEN-2024-240, Nowata County
Onshore wind
300 MWIn study Nowata, OKSPP Mar 2025target 2029
Onshore wind project GEN-2021-057, Antelope County
Onshore wind
300 MWIn study Antelope, NESPP Apr 2021target 2027
Solar + storage project GEN-2024-215, Cloud County
Solar + storage
300 MWIn study Cloud, KSSPP Mar 2025target 2029
Solar project GEN-2023-099, Jackson County
Solar
300 MWIn study Jackson, KSSPP Oct 2023target 2030
Solar project GEN-2022-013, Bourbon County
Solar
300 MWIn study Bourbon, KSSPP Jun 2022target 2028
Solar project GEN-2024-226, Hempstead County
Solar
300 MWIn study Hempstead, ARSPP Mar 2025target 2030
Battery storage project GEN-2024-230, Wilbarger County
Battery storage
300 MWIn study Wilbarger, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-138, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Solar + storage project GEN-2024-050, Castro County
Solar + storage
300 MWIn study Castro, TXSPP Oct 2024target 2028
Onshore wind project GEN-2024-142, Mcpherson County
Onshore wind
300 MWIn study Mcpherson, KSSPP Mar 2025target 2031
Gas project GEN-2024-253, Leavenworth County
Gas
300 MWIn study Leavenworth, KSSPP Mar 2025target 2027
Onshore wind project GEN-2017-014, Haakon County
Onshore wind
300 MWAgreement signed Haakon, SDSPP May 2017target 2027
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Battery storage project GEN-2024-339, Leavenworth County
Battery storage
300 MWIn study Leavenworth, KSSPP Mar 2025target 2029
Solar + storage project GEN-2024-336, Yoakum County
Solar + storage
300 MWIn study Yoakum, TXSPP Mar 2025target 2029
Battery storage project GEN-2024-SR15, Yoakum County
Battery storage
300 MWIn study Yoakum, TXSPP Oct 2024target 2026
Gas project GEN-2024-255, Oklahoma County
Gas
300 MWIn study Oklahoma, OKSPP Mar 2025target 2027
Onshore wind project GEN-2024-016, Smith County
Onshore wind
300 MWIn study Smith, KSSPP Oct 2024target 2028
Onshore wind project GEN-2017-151, Crosby County
Onshore wind
300 MWAgreement signed Crosby, TXSPP Nov 2017target 2026
Onshore wind project GEN-2018-099, Parmer County
Onshore wind
300 MWAgreement signed Parmer, TXSPP Nov 2018target 2027
Onshore wind project GEN-2023-107, Finney County
Onshore wind
300 MWIn study Finney, KSSPP Oct 2023target 2030
Solar + storage project GEN-2024-364, Randall County
Solar + storage
300 MWIn study Randall, TXSPP Mar 2025target 2028
Battery storage project GEN-2025-SR16, Sumner County
Battery storage
300 MWIn study Sumner, KSSPP Jun 2025target 2026
Solar project GEN-2024-317, Cottle County
Solar
300 MWIn study Cottle, TXSPP Mar 2025target 2030
Onshore wind project GEN-2024-144, Scott County
Onshore wind
300 MWIn study Scott, KSSPP Mar 2025target 2030
Onshore wind project GEN-2017-181, Lancaster County
Onshore wind
300 MWAgreement signed Lancaster, NESPP Nov 2017target 2028
Solar project GEN-2024-077, Hutchinson County
Solar
300 MWIn study Hutchinson, TXSPP Oct 2024target 2029
Solar project GEN-2024-159, Roosevelt County
Solar
300 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-331, Dunn County
Battery storage
300 MWIn study Dunn, NDSPP Mar 2025target 2028
Solar project GEN-2024-068, Morris County
Solar
300 MWIn study Morris, TXSPP Oct 2024target 2028
Gas project GEN-2024-252, Canadian County
Gas
300 MWIn study Canadian, OKSPP Mar 2025target 2027
Battery storage project GEN-2022-073, Clay County
Battery storage
300 MWIn study Clay, MOSPP Sep 2022target 2030
Onshore wind project GEN-2025-GR6, Dimmit County
Onshore wind
300 MWIn study Dimmit, TXSPP Nov 2025
Onshore wind project GEN-2024-GR6, Kay County
Onshore wind
300 MWIn study Kay, OKSPP Jul 2024target 2027
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Solar project GEN-2020-054, Bowie County
Solar
298 MWAgreement signed Bowie, TXSPP Apr 2020target 2027
Onshore wind project GEN-2017-137, Oklahoma County
Onshore wind
295 MWAgreement signed Oklahoma, OKSPP Nov 2017target 2030
Solar project GEN-2022-016, Woodward County
Solar
288 MWIn study Woodward, OKSPP Jun 2022target 2028
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Page 3 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)