🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nebraska

ONSHORE WIND · SPP

Onshore wind project GEN-2021-057, Antelope County

Onshore wind project GEN-2021-057, Antelope County is a 300 MW onshore wind request in interconnection study in the SPP interconnection queue, in Antelope County, Nebraska, connecting to NPPD.

Queue statusIn planning
  1. PlanningQueued Apr 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2021-057
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Antelope 345kV substation
Location
Antelope County, Nebraska
Technology
Wind: 300 MW
Total requested
300 MW
Service type
Energy only (ERIS)
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
29 April 2021
Proposed online date
December 2027

Location

Marker shows the centre of Antelope County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Antelope County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem