Solar project GEN-2018-044, Antelope County

Solar project GEN-2018-044, Antelope County is a 500 MW solar request withdrawn in the SPP interconnection queue, in Antelope County, Nebraska, connecting to OPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2018 (completed)
  2. Withdrawn / abandonedApr 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2018-044
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OPPD
Connection point (POI)
Fort Calhoun 345kV Substation
Location
Antelope County, Nebraska
Technology
Solar: 500 MW
Total requested
500 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 May 2018
Proposed online date
December 2025
Came online
December 2025
Withdrawn
April 2023

Location

Marker shows the centre of Antelope County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Antelope County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem