ONSHORE WIND · SPP

Onshore wind project GEN-2015-023, Antelope County

Onshore wind project GEN-2015-023, Antelope County is a 301 MW onshore wind request built and operating in the SPP interconnection queue, in Antelope County, Nebraska, connecting to NPPD.

Queue statusOperating
  1. PlanningQueued Mar 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-023
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Connection point (POI)
Grand Prairie-Grand Island (Holt County NE) 345kV
Location
Antelope County, Nebraska
Technology
Wind: 301 MW
Total requested
301 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
31 March 2015
Proposed online date
April 2024
Came online
November 2022

Location

Marker shows the centre of Antelope County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Antelope County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem