Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,249298.6 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,249 requests ยท page 25 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AI2-350, Queen Anne's County
Solar
11.9 MWIn study Queen Anne's, MDPJM Mar 2023target 2025
Clutch City Storage II SLF
Battery storage
11.3 MWPaused / redesign Brazoria, TXERCOT Feb 2023
Panther Creek 1 Repower
Onshore wind ยท Panther Creek Wind Farm I&II, LLC
11.0 MWIn study Glasscock, TXERCOT Jun 2023target 2026
Solar project AI2-349, Marion County
Solar
11.0 MWIn study Marion, KYPJM Mar 2023target 2029
Solar project AI2-430, Dekalb County
Solar
11.0 MWIn study Dekalb, INPJM Mar 2023target 2023
Damon BESS 2
Battery storage ยท PR DAMON, LLC
10.0 MWAgreement signed Brazoria, TXERCOT May 2023target 2026
Other project 897773, Johnston County
Other
10.0 MWUnder construction Johnston, NCSoutheast Jun 2023target 2026
Wildhorse POD Solar
Solar ยท Highpeak Solar, LLC
10.0 MWPaused / redesign Howard, TXERCOT Oct 2023target 2026
Harris Spencer BESS
Other ยท Harris Spencer BESS, LLC
10.0 MWPaused / redesign Harris, TXERCOT Mar 20232025
Solar project G1004, Franklin County
Solar
10.0 MWIn study Franklin, WAWest Nov 2023target 2025
Solar project G0957, Benton County
Solar
10.0 MWIn study Benton, WAWest Oct 2023target 2027
Cedro Hill Wind Repower
Onshore wind ยท CEDRO HILL WIND LLC
9.9 MWAgreement signed Webb, TXERCOT Sep 2023target 2026
Hidden Lakes BESS
Battery storage ยท SBESS TX 6 LLC
9.9 MWAgreement signed Galveston, TXERCOT Jun 2023target 2026
Gears BESS
Battery storage ยท Regis Gears-Harris LLC
9.9 MWAgreement signed Harris, TXERCOT Jun 2023target 2026
Chocolate Bayou BESS
Battery storage ยท Concurrent Holdco. , LLC.
9.9 MWIn study ERCOT Aug 2023target 2026
Solar project AI2-398, Preble County
Solar
9.6 MWIn study Preble, OHPJM Mar 2023target 2026
Panther Creek 2 Repower
Onshore wind ยท Panther Creek Wind Farm I&II, LLC
8.0 MWIn study Glasscock, TXERCOT Jun 2023target 2026
Solar project AI2-310, Venango County
Solar
7.3 MWIn study Venango, PAPJM Mar 2023target 2025
Gas project 192, Anderson County
Gas
7.0 MWIn study Anderson, SCSoutheast Jun 2023
Gas project 193, Anderson County
Gas
7.0 MWIn study Anderson, SCSoutheast Jun 2023
Hydro project 590, Marion County
Hydro
7.0 MWIn study Marion, TNSoutheast Nov 2023target 2028
Gas project 194, Anderson County
Gas
7.0 MWIn study Anderson, SCSoutheast Jun 2023
Solar project AI2-057, Venango County
Solar
6.6 MWIn study Venango, PAPJM Feb 2023target 2024
Hydro project 899433, Montgomery County
Hydro ยท Duke Energy Progress, LLC
6.3 MWUnder construction Montgomery, NCSoutheast Jun 2023
Solar project AI2-458, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-476, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AI2-467, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-469, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-459, Berks County
Solar
5.8 MWIn study Berks, PAPJM Mar 2023target 2027
Solar project AI2-470, Mercer County
Solar
5.8 MWIn study Mercer, PAPJM Mar 2023target 2027
Solar project AI2-477, Bedford County
Solar
5.8 MWIn study Bedford, PAPJM Mar 2023target 2027
Solar project AI2-312, Venango County
Solar
5.5 MWIn study Venango, PAPJM Mar 2023target 2022
Solar project AI2-043, Northumberland County
Solar
5.0 MWIn study Northumberland, VAPJM Jan 2023target 2024
Solar Increase
Solar
5.0 MWIn study Hartford, CTISO-NE Feb 2023target 2027
Solar + storage project 440, Lewis And Clark County
Solar + storage
4.6 MWIn study Lewis And Clark, MTWest Jan 2023target 2023
Solar project AI2-308, Bedford County
Solar
4.4 MWIn study Bedford, PAPJM Mar 2023target 2024
Battery storage project 889853, Vance County
Battery storage
3.6 MWUnder construction Vance, NCSoutheast Jun 2023
Solar + storage project IC-1199, Lowndes County
Solar + storage
3.5 MWAgreement signed Lowndes, GASoutheast Nov 2023target 2025
CPS Rio Nogales CT301 Rotor Replacement
Gas ยท CPS Energy
3.1 MWAgreement signed Guadalupe, TXERCOT Jul 2023target 2025
Solar project C3-148, Crook County
Solar ยท CP Prineville, LLC
3.0 MWIn study Crook, ORWest May 2023target 2033
Solar project G1003, Adams County
Solar
3.0 MWIn study Adams, WAWest Nov 2023target 2025
Other project 897777, Wake County
Other
2.0 MWUnder construction Wake, NCSoutheast Jun 2023target 2025
Solar project 454, Gallatin County
Solar
2.0 MWIn study Gallatin, MTWest Dec 2023target 2024
Hydro project 897387, Macon County
Hydro
2.0 MWUnder construction Macon, NCSoutheast Jun 2023
Hydro project 899609, Jackson County
Hydro
1.8 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026
Hydro project 899793, Jackson County
Hydro
1.5 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026
Solar project G0943, Snohomish County
Solar
1.0 MWIn study Snohomish, WAWest Oct 2023target 2024
Solar project G0968, Clark County
Solar
1.0 MWIn study Clark, WAWest Oct 2023target 2023
Champion Wind Repower
Onshore wind ยท Champion Wind Farm, LLC
0.3 MWAgreement signed Nolan, TXERCOT Sep 2023target 2025
Page 25 of 25

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)