Hydro project 899433, Montgomery County

Hydro project 899433, Montgomery County is a 6.3 MW hydro request under construction in the Southeast interconnection queue, in Montgomery County, North Carolina, connecting to Duke Energy Progress.

Queue statusUnder construction
  1. PlanningQueued Jun 2023 (completed)
  2. Consented (completed)
  3. Construction (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
899433
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Developer
Duke Energy Progress, LLC
Connection point (POI)
Tillery Hydro Plant Substation
Location
Montgomery County, North Carolina
Technology
Hydro: 6.3 MW
Total requested
6.3 MW
Service type
Network resource (NRIS)
Study phase
Construction - Pending
Queue status
Active
Entered queue
28 June 2023

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem