🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › North Carolina

HYDRO · SOUTHEAST

Hydro project PP00033, Montgomery County

Hydro project PP00033, Montgomery County is a 6.3 MW hydro request in interconnection study in the Southeast interconnection queue, in Montgomery County, North Carolina, connecting to Duke Energy Progress.

Queue statusIn planning
  1. PlanningQueued Jun 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
PP00033
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Progress
Connection point (POI)
Tillery Hydroelectric Plant Switchyard (T1590)
Location
Montgomery County, North Carolina
Technology
Hydro: 6.3 MW
Total requested
6.3 MW
Study phase
Tender Provisional Study Agreement
Queue status
Active
Entered queue
16 June 2025
Proposed online date
June 2026

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in North Carolina · Transmission lines in North Carolina

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem