Solar project G0968, Clark County

Solar project G0968, Clark County is a 1.0 MW solar request in interconnection study in the West interconnection queue, in Clark County, Washington.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0968
Grid region
West (non-ISO utilities)
Connection point (POI)
Evans Substation
Location
Clark County, Washington
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
13 October 2023
Proposed online date
December 2023

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.