GAS Β· WEST

Clark Public Utilities

Clark Public Utilities is a 250 MW gas request withdrawn in the West interconnection queue, in Clark County, Washington, connecting to Clark Public Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2001 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G46-01
Grid region
West (non-ISO utilities)
Utility / transmission owner
Clark Public Utilities
Connection point (POI)
115 kV bus at BPA Alcoa Substation
Location
Clark County, Washington
Technology
Gas: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Queue status
Withdrawn
Entered queue
17 April 2001
Proposed online date
July 2002

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Clark County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem