🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Hidden Lakes BESS

Hidden Lakes BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Galveston County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedFeb 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0617
Grid region
ERCOT (Texas)
Developer
SBESS TX 6 LLC
Connection point (POI)
Station Name: HDNLAKES PTI Bus#: 38900 Load XFMR Name: HDLAKE_2 Transmission Level Voltage: 138 kV
Location
Galveston County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
14 June 2023
Agreement signed
7 February 2024
Proposed online date
May 2026

Location

Marker shows the centre of Galveston County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Galveston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem