BATTERY STORAGE · ERCOT

Southern Select Energy Storage

Southern Select Energy Storage is a 205 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Galveston County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2023 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0340
Grid region
ERCOT (Texas)
Developer
SOUTHERN SELECT ENERGY STORAGE LLC
Connection point (POI)
Bus Name: TNHEIGHTS_1 Bus Number: 38740
Location
Galveston County, Texas
Technology
Battery: 205 MW
Total requested
205 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
25 October 2023
Agreement signed
9 May 2025
Proposed online date
March 2027

Location

Marker shows the centre of Galveston County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Galveston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem