United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTWizard BESS
Wizard BESS is a 151 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Galveston County, Texas.
Queue statusConsented
- PlanningQueued Mar 2023 (completed)
- ConsentedAug 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 25INR0300
- Grid region
- ERCOT (Texas)
- Developer
- Wizard Energy Storage, LLC
- Connection point (POI)
- To the 138 kV League City Substation (#38920)
- Location
- Galveston County, Texas
- Technology
- Battery: 151 MW
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 27 March 2023
- Agreement signed
- 21 August 2023
- Proposed online date
- February 2026
Location
Marker shows the centre of Galveston County; the queue data does not give exact sites.
Other requests in Galveston County
- Red Egret BESSBattery storage · 311 MW · agreement signed
- Shepard Energy StorageBattery storage · 257 MW · agreement signed
- Zeya BESSBattery storage · 255 MW · agreement signed
- Vertus Energy StorageBattery storage · 207 MW · agreement signed
- Southern Select Energy StorageBattery storage · 205 MW · agreement signed
- Air Products GCAGas · 14.0 MW · agreement signed
- Hidden Lakes BESSBattery storage · 9.9 MW · agreement signed
- Hecate Energy Jamaica WindOnshore wind · 1,029 MW · in study
- Hacienda StorageBattery storage · 202 MW · in study
- Kresge Land Battery StorageBattery storage · 200 MW · in study
- Valcrest BESSBattery storage · 154 MW · in study
- IEP BlackhawkBattery storage · 100 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem