Shepard Energy Storage

Shepard Energy Storage is a 257 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Galveston County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2022 (completed)
  2. ConsentedJan 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0262
Grid region
ERCOT (Texas)
Developer
Shepard Energy Storage LLC
Connection point (POI)
Hidden Lakes 138kV substation (Bus# 38900)
Location
Galveston County, Texas
Technology
Battery: 257 MW
Total requested
257 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
15 December 2022
Agreement signed
17 January 2024
Proposed online date
July 2027

Location

Marker shows the centre of Galveston County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Galveston County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem