Zeya BESS

Zeya BESS is a 255 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Galveston County, Texas.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0290
Grid region
ERCOT (Texas)
Developer
BRP Zeya BESS LLC
Connection point (POI)
38740 Heights 138kV
Location
Galveston County, Texas
Technology
Battery: 255 MW
Total requested
255 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
31 May 2021
Agreement signed
20 January 2023
Proposed online date
December 2026

Location

Marker shows the centre of Galveston County; the queue data does not give exact sites.