Damon BESS 2

Damon BESS 2 is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusConsented
  1. PlanningQueued May 2023 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0603
Grid region
ERCOT (Texas)
Developer
PR DAMON, LLC
Connection point (POI)
9.99 MW 50 MWh battery energy storage project connecting at 12.47kV Damon (DA) substation. Station Name (TDSP Station Code): DA Load/Load Transformer Name: TR2 PTI BUS number: 42370 Voltage in kV (Tr
Location
Brazoria County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
17 May 2023
Agreement signed
6 October 2023
Proposed online date
August 2026

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.