United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Gears BESS

Gears BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Harris County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2023 (completed)
  2. ConsentedSep 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0595
Grid region
ERCOT (Texas)
Developer
Regis Gears-Harris LLC
Connection point (POI)
Station Name (TSP Station Code): Gears (GZ) Load/Load Transformer Name: TR1 PTI Bus Number: 45781 Voltage in kV (Transmission Level): 138 kV
Location
Harris County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
28 June 2023
Agreement signed
20 September 2023
Proposed online date
January 2026

Location

Marker shows the centre of Harris County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Harris County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem