Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,249298.6 GW
Active in queue298.6 GW1,249 requests
Agreement signed34.6 GW168 requests
Withdrawn2,063551.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,249 requests ยท page 22 of 25
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 239, Marion County
Solar
55.0 MWIn study Marion, SCSoutheast Jun 2023target 2027
Solar project GEN-2023-135, Bowie County
Solar
52.0 MWIn study Bowie, TXSPP Oct 2023target 2026
Orchard Ray BESS
Battery storage ยท Pettus BESS
51.9 MWIn study Bee, TXERCOT Jun 2023target 2027
Solar project AI2-196, Lycoming County
Solar
51.5 MWIn study Lycoming, PAPJM Mar 2023target 2025
Proving Ground BESS
Solar + storage ยท Lantana Solar LLC
51.4 MWIn study Schleicher, TXERCOT Jul 2023target 2028
Solar project Q104, Pinal County
Solar
51.3 MWIn study Pinal, AZWest May 2023target 2025
Ayass BESS
Battery storage ยท Harvick BESS, LLC
51.3 MWIn study Throckmorton, TXERCOT Dec 2023target 2028
Black Bear BESS
Solar + storage ยท ESCONDIDO DRAW RESOURCES, LLC
51.2 MWIn study Crockett, TXERCOT Dec 2023target 2028
Lupinus Storage 3
Solar + storage ยท Lupinus Solar 2, LLC
50.9 MWAgreement signed Franklin, TXERCOT Sep 2023target 2026
Stegall Storage
Solar + storage ยท BT Martin Solar, LLC
50.5 MWIn study Robertson, TXERCOT Aug 2023target 2027
Surfside Energy Storage
Battery storage ยท Rocky Mountain Energy Holdings, LLC
50.3 MWIn study Brazoria, TXERCOT Jul 2023target 2028
Solar project AI2-244, Nottoway County
Solar
50.3 MWIn study Nottoway, VAPJM Mar 2023target 2028
Marick Rose BESS
Battery storage ยท Marick BESS
50.2 MWIn study Fort Bend, TXERCOT Jul 2023target 2026
Fort Chadbourne Cattle BESS
Battery storage ยท Fort Chadbourne BESS
50.2 MWIn study Coke, TXERCOT Aug 2023target 2027
Beeman BESS
Battery storage ยท Beeman BESS LLC
50.2 MWIn study Gonzales, TXERCOT Apr 2023target 2027
Battery storage project GEN-2023-SR9, Crosby County
Battery storage
50.0 MWAgreement signed Crosby, TXSPP Feb 2023target 2026
Battery storage project AJ1-001, Mecklenburg County
Battery storage
50.0 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Surplus; J1369
Other
50.0 MWIn study Dubois, INMISO Apr 2023target 2024
Battery storage project AI2-042, Louisa County
Battery storage
50.0 MWIn study Louisa, VAPJM Feb 2023target 2026
Battery storage project GEN-2023-SR19, Jefferson County
Battery storage
50.0 MWIn study Jefferson, NESPP Jun 2023target 2026
Solar project AI2-416, Augusta County
Solar
50.0 MWIn study Augusta, VAPJM Mar 2023target 2026
Solar + storage project GI-2023-165, Imperial County
Solar + storage
50.0 MWIn study Imperial, CAWest Jan 2023target 2025
Battery storage project GEN-2023-206, Sebastian County
Battery storage
50.0 MWIn study Sebastian, ARSPP Oct 2023target 2029
Battery storage project 23-05032, Larimer County
Battery storage
50.0 MWIn study Larimer, COWest May 2023target 2026
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO Apr 2023target 2024
Battery storage project 23-05031, Boulder County
Battery storage
50.0 MWIn study Boulder, COWest May 2023target 2026
Battery storage project 23-08081, Larimer County
Battery storage
50.0 MWIn study Larimer, COWest Aug 2023target 2026
Solar + storage project AI2-030, Adams County
Solar + storage
50.0 MWIn study Adams, OHPJM Jan 2023target 2024
Replacing 49 MW of gas generation with BESS; Sterlington
Other
49.0 MWIn study Ouachita, LAMISO Oct 2023target 2025
Solar project AJ1-022, Mecklenburg County
Solar
49.0 MWIn study Mecklenburg, VAPJM Jun 2023target 2027
Solar project AI2-161, Vermillion County
Solar
48.0 MWIn study Vermillion, INPJM Mar 2023target 2025
Solar project AI2-151, Logan County
Solar
48.0 MWIn study Logan, ILPJM Feb 2023target 2025
Solar project AI2-162, Whitley County
Solar
48.0 MWIn study Whitley, INPJM Mar 2023target 2025
Solar project AI2-417, Dekalb County
Solar
48.0 MWIn study Dekalb, ILPJM Mar 2023target 2026
Gas project 899591, Richmond County
Gas ยท Duke Energy Progress, LLC
46.8 MWAgreement signed Richmond, NCSoutheast Jun 2023
Gas project GI-117, New Madrid County
Gas
46.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Battery storage project AI2-277, Greensville County
Battery storage
45.0 MWIn study Greensville, VAPJM Mar 2023target 2026
Solar project AI2-150, Huntington County
Solar
44.4 MWIn study Huntington, INPJM Feb 2023target 2025
Solar project 920663, Randolph County
Solar
44.0 MWIn study Randolph, NCSoutheast Sep 2023
Solar project IC-1203, Jasper County
Solar
44.0 MWAgreement signed Jasper, MSSoutheast Nov 2023target 2028
Solar project AI2-159, Miami County
Solar
43.5 MWIn study Miami, OHPJM Mar 2023target 2027
Solar project AI2-421, Dekalb County
Solar
43.2 MWIn study Dekalb, INPJM Mar 2023target 2027
Solar project AI2-426, Allen County
Solar
43.2 MWIn study Allen, INPJM Mar 2023target 2027
Old Sorrell Energy Storage
Battery storage
43.1 MWPaused / redesign Concho, TXERCOT Jun 2023
Pamplona Solar
Solar + storage ยท Karol Solar III
42.4 MWIn study Austin, TXERCOT Aug 2023target 2028
Solar project AI2-079, Fauquier County
Solar
40.7 MWIn study Fauquier, VAPJM Feb 2023target 2025
Solar project AI2-060, Henry County
Solar
40.7 MWIn study Henry, ILPJM Feb 2023target 2024
Solar project AI2-475, Montour County
Solar
40.6 MWIn study Montour, PAPJM Mar 2023target 2026
Surplus; J1102
Other
40.0 MWIn study Logan, ILMISO Oct 2023target 2025
Solar project CS23-13, Lincoln County
Solar
40.0 MWAgreement signed Lincoln, WAWest May 2023target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)