United States › Grid › Interconnection queues › Nebraska
BATTERY STORAGE · SPPBattery storage project GEN-2023-SR19, Jefferson County
Battery storage project GEN-2023-SR19, Jefferson County is a 50.0 MW battery storage request in interconnection study in the SPP interconnection queue, in Jefferson County, Nebraska, connecting to NPPD.
- PlanningQueued Jun 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2023-SR19
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Steele City 115 kV
- Location
- Jefferson County, Nebraska
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- FACILITY STUDY STAGE
- Queue status
- Active
- Entered queue
- 21 June 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Jefferson County; the queue data does not give exact sites.
Other requests in Jefferson County
- Onshore wind project GEN-2011-018, Jefferson CountyOnshore wind · 73.6 MW · built
- Onshore wind project GEN-2014-004, Jefferson CountyOnshore wind · 4.0 MW · built
- Onshore wind project GEN-2013-008, Jefferson CountyOnshore wind · 1.2 MW · built
- Onshore wind project GEN-2023-011, Jefferson CountyOnshore wind · 190 MW · withdrawn
- Onshore wind project GEN-2015-100, Jefferson CountyOnshore wind · 120 MW · withdrawn
- Onshore wind project GEN-2016-109, Jefferson CountyOnshore wind · 102 MW · withdrawn
- Onshore wind project GEN-2006-038N004, Jefferson CountyOnshore wind · 100 MW · withdrawn
- Onshore wind project GEN-2010-044, Jefferson CountyOnshore wind · 99.0 MW · withdrawn
- Onshore wind project GEN-2014-006, Jefferson CountyOnshore wind · 74.9 MW · withdrawn
- Onshore wind project GEN-2010-047, Jefferson CountyOnshore wind · 72.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem