ONSHORE WIND Β· SPP

Onshore wind project GEN-2006-038N004, Jefferson County

Onshore wind project GEN-2006-038N004, Jefferson County is a 100 MW onshore wind request withdrawn in the SPP interconnection queue, in Jefferson County, Nebraska, connecting to NPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2006 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2006-038N004
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
NPPD
Location
Jefferson County, Nebraska
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
17 October 2006
Proposed online date
October 2006

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Nebraska Β· Transmission lines in Nebraska

Other requests in Jefferson County