Marick Rose BESS

Marick Rose BESS is a 50.2 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusIn planning
  1. PlanningQueued Jul 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0487
Grid region
ERCOT (Texas)
Developer
Marick BESS
Connection point (POI)
Tap 138kV 44521 Marick - 44615 Rosenberg Ckt 60
Location
Fort Bend County, Texas
Technology
Battery: 50.2 MW
Total requested
50.2 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
10 July 2023
Proposed online date
May 2026

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem